RiskLock Unlocked: Analysing the ‘Phantom Supply’ Stalling Australian Construction
The Australian construction and property development sector is currently navigating a period of profound structural dissonance, a phenomenon this report classifies as “RiskLock.” This condition is defined by a widening chasm between bureaucratic ambition, manifested in government housing targets and Development Approval (DA) volumes, and commercial reality, where actual project commencements are stagnating or collapsing.
The Paradox of the Pipeline
The Australian construction and property development sector is currently navigating a period of profound structural dissonance, a phenomenon this report classifies as “RiskLock.” This condition is defined by a widening chasm between bureaucratic ambition, manifested in government housing targets and Development Approval (DA) volumes, and commercial reality, where actual project commencements are stagnating or collapsing.
The central hypothesis of “Phantom Supply” posits that a significant proportion of the “approved” pipeline is, for all practical commercial purposes, dead stock. These projects are trapped in a feasibility void where the cost of construction, driven by a fundamental repricing of risk by Tier 1 and Tier 2 builders, exceeds the realisation value of the asset.
The investigation into the “Risk Premium” tender refusals and pipeline stagnation confirms that the market has exited the “profitless boom” of the 2022–2024 period and entered a new cycle of “Margin Rebuild” and “Risk Blockade.” During the previous cycle, builders operated on razor-thin margins of 2-4%, absorbing hyper-escalation in materials and labour, which led to a wave of high-profile insolvencies. The surviving contractor base has responded with a defensive pivot, enforcing a blockade against fixed-price contracting and demanding net margins of 8-10% to insulate against future volatility. This shift is not merely cyclical but structural, representing a permanent alteration in the risk allocation architecture of the Australian construction industry.
Four Structural Drivers of Stagnation
To test the “RiskLock” dynamic, this analysis examines four structural drivers:
- The Tender Refusal Rate: The market is witnessing a collapse in competitive tension. The anecdotal “40% decline to tender” is validated functionally by the thinning of bid lists. Tier 1 builders are exercising extreme selectivity, declining invitations to tender (ITT) on projects that do not meet strict risk/reward criteria, effectively creating a “Phantom Tender” market where developers struggle to secure compliant bids.
- The Margin Rebuild: The cost of construction has structurally increased not just through input costs, but through the expansion of the builder’s margin. The shift from 2% survival margins to 8-10% sustainability margins represents a massive escalation in the total development cost stack, rendering many previously approved projects unfeasible.
- The Approved-to-Commenced Drop-off: Analysis of ABS and KPMG data confirms a growing backlog of “stalled stock,” particularly in Brisbane and Perth. This stock is approved but uncommenced due to the inability to lock in a builder at a viable price. In Brisbane, this is exacerbated by the crowding-out effect of Olympic infrastructure; in Perth, by the resource sector’s absorption of labour capacity.
- The Contractual Pivot: The industry is aggressively migrating away from Fixed Price Lump Sum (FPLS) contracts toward Early Contractor Involvement (ECI) and Management Contracting. This pivot extends the pre-construction phase and transfers risk back to the developer, further slowing the transition from approval to commencement.
The remainder of this brief examines each of these drivers in turn, drawing on Q4 2025 and 2026 market intelligence, to test whether the market’s stagnation is structural rather than cyclical.
The Mechanics of the “Risk Blockade”
The “Risk Blockade” is the operational manifestation of the construction sector’s newfound risk aversion. Following the traumatic insolvency events of 2023 and 2024, where major firms like Porter Davis collapsed due to fixed-price exposure, the surviving Tier 1 and upper-Tier 2 builders have adopted a “survival first” strategy. This strategy hinges on the refusal to tender for projects that present unquantifiable risks or adversarial contract terms.
While the specific statistic of a “40% decline to tender” is widely cited in industry discussion, the research validates this through the proxy of “Bid Coverage.” Historically, a developer might expect 5 to 6 compliant bids for a major residential or commercial project. In the current 2025/2026 climate, this bid coverage has collapsed to 2 to 3 bids, and often effectively zero for high-risk projects. This reduction in participation represents a functional decline in tender capacity of approximately 40-50%, aligning with the hypothesis.
The Driver: Insolvency Avoidance and Selective Bidding
The primary driver of tender refusal is the fear of the “Winner’s Curse”, the statistical probability that the winning bidder is the one who most severely underestimated the costs or risks of the project. In a low-margin environment, winning a project with an underestimated cost base is a direct path to administration.
- Selective Bidding as a Strategy: Rider Levett Bucknall (RLB) explicitly notes in their Q4 2025 reporting that limited competition in the Tier 1 subcontractor market is driving “selective bidding,” with contractors focusing entirely on lower-risk projects. This selectivity is a luxury afforded by the sheer volume of work available in the infrastructure and public sectors. Builders are no longer desperate for turnover; they are desperate for safe turnover.
- The “No-Bid” Decision Matrix: Builders are employing sophisticated “Go/No-Go” decision matrices before even accepting tender documents. Factors that trigger an immediate “Decline to Tender” include:
- Fixed Price Contracts: Any insistence on a hard-dollar Fixed Price Lump Sum (FPLS) without rise-and-fall provisions is a primary trigger for refusal.
- Incomplete Design: Projects attempting to tender on 50-60% design documentation (historically common) are now rejected. Builders demand 90%+ design certainty or an ECI engagement.
- Client Reputation: Developers with a history of litigious behaviour, slow payment, or aggressive superintendent administration are being blacklisted by Tier 1 firms.
The “Phantom Tender” Phenomenon
A secondary phenomenon distorting the market is the “Phantom Tender” or “Cover Pricing.” In some instances, builders may not explicitly decline a tender invitation to avoid damaging a long-term relationship, but will instead submit a “Cover Price.” This is a bid intentionally priced 15-20% above the market rate to ensure the builder does not win the project unless the margin is extraordinarily high.
AS Estimation notes that when bid coverage is thin, contractor margin adjustments often increase because contractors can be selective. This behaviour masks the true extent of the refusal rate. A developer may receive three bids, but if two are cover prices and one is a risk-laden high bid, the project is effectively un-tendered in competitive terms. This contributes to the “Phantom Supply” problem; the project technically has market pricing, but that pricing is commercially unfeasible, leaving the project stalled.
The Tier 1 Withdrawal and Public Sector Crowding Out
The “Risk Blockade” is most acute at the Tier 1 level. These firms have the strongest balance sheets and the most rigorous internal risk controls. They are increasingly pivoting their order books toward government-funded infrastructure (hospitals, defence, transport) and institutional-grade assets like data centres.
- Data Centre Absorption: The surge in data centre construction, driven by AI demand, is absorbing a disproportionate amount of Tier 1 capacity. With data centre construction growing by 33% in 2025 and projected to grow another 20% in 2026, Tier 1 builders are prioritising these highly technical, well-funded projects over speculative residential developments.
- Public Infrastructure Security: Government projects offer security of payment, often operate on collaborative contracting models (Alliance or Managing Contractor), and provide rise-and-fall mechanisms for material costs. For a risk-averse builder, choosing between a government hospital and a private apartment tower is a choice between stability and potential insolvency. This “crowding out” effect leaves the private sector starved of Tier 1 capacity, forcing them to engage with less capitalised Tier 2 builders or stall the project entirely.
NIL RETURN Statement
NIL RETURN: While the “40% decline to tender” figure is consistent with the observed reduction in bid list density (from ~5 to ~3 bidders), no specific statistical report from RLB, AS Estimation, or WT Partnership explicitly tabulates a “40% Refusal Rate” as a singular data point in the cited 2025/2026 industry reporting. The figure remains a valid derivative metric describing the collapse in bid coverage and competitive tension.
The End of the “Profitless Boom” (2022-2024)
The construction industry is emerging from a period characterised as a “profitless boom.” Between 2022 and 2024, builders experienced high turnover due to stimulus-induced demand (e.g., HomeBuilder) and the post-COVID pipeline. However, this turnover was often generated on legacy fixed-price contracts signed prior to the inflation spike.
- The 2-4% Era: During this period, builders typically operated on net profit margins of 2-4%. In many cases, actual realised margins were negative due to cost escalation exceeding the total profit allowance. This era eroded the working capital of the entire supply chain, leading to the collapse of major volume builders and a thinning of the subcontractor market.
- Balance Sheet Erosion: The survival of many firms during this period was predicated on cash flow rather than profit, using the deposit from New Project B to pay the debts of Old Project A. This precarious model has now collapsed, necessitating a fundamental restructuring of how builders price their services.
The 2026 Target: 8-10% Net Margins
The research confirms a decisive shift in 2025/2026 toward a “Margin Rebuild.” Builders are no longer willing to price work at “survival” margins. The new target for sustainable operation, particularly for Tier 1 and stable Tier 2 builders, is a net profit margin of 8-10%.
- Industry Guidance: Industry analysis suggests that “healthy general contractors should target 8-10% net margins,” a significant increase from the historical norm of 2-5%. This target is driven by the need to:
- Repair Balance Sheets: Builders must generate retained earnings to replenish the capital burned during the 2022-2024 crisis.
- Finance Growth: High interest rates increase the cost of working capital. Builders cannot rely on cheap credit to float project cash flows; they must be self-funding.
- Buffer Against Risk: The “Risk Pot” or contingency within the margin must be larger to accommodate the continued volatility of the labour market and supply chain.
Table 1: The Margin Shift (Survival vs. Rebuild)
| Margin Component | 2022-2024 “Survival” Model | 2025-2026 “Rebuild” Model | Strategic Driver |
|---|---|---|---|
| Net Profit Margin | 1.0% – 3.0% (often 0% realised) | 8.0% – 10.0% | Insolvency avoidance; Capital repair. |
| Gross Margin | 8.0% – 12.0% | 15.0% – 25.0% | Coverage of bloated overheads & prelims. |
| Risk Pricing | Implicit / Absorbed | Explicit (3-5%) | Risk is now a non-negotiable line item. |
| Preliminaries | Compressed (Competitive) | Expanded (Time-Risk) | Labour shortages extend programmes, increasing time costs. |
The “Cost Stack” Expansion
It is critical to understand that the “Margin Rebuild” is not simply a builder asking for more profit; it is an expansion of the entire “Cost Stack.” The final tender price received by a developer in 2026 is structurally higher than in 2024 due to the compounding effect of several factors:
- Preliminaries Blowout: AS Estimation warns that longer jobs increase labour, preliminaries, and risk costs. The labour shortage means projects take longer to build. A 24-month programme becoming a 30-month programme increases the “Preliminaries” (site management, scaffolding, cranes) by 25%. This cost is added before the margin is applied.
- Productivity Drag: The “Phantom Cost” in the stack is low productivity. Even if hourly wage rates were stable (which they are not), the cost per unit of output has risen because it takes more hours to do the same work. Rework, RFIs, and coordination issues due to inexperienced staff are driving this productivity drag.
- The Risk Pot: In 2024, builders might have absorbed risk to win work. In 2026, tenders include explicit “Risk Pricing.” This acts as a secondary margin. A project costing $100m might now include a $5m “Risk Allowance” line item. This is money the developer pays to insure the builder against volatility.
Sector-Specific Margin Dynamics
The “Margin Rebuild” manifests differently across sectors:
- Residential (Volume): Volume builders are under the most pressure. While they attempt to push margins to 20-25% (gross), they are constrained by consumer borrowing capacity. However, the days of the fixed-price house and land package with a thin margin are over. Builders who track finances closely are achieving net margins of 8.5%, while those who do not are languishing at 4-5%.
- Commercial / Tier 1: This sector is strictly adhering to the 8-10% net target. Projects that fail to demonstrate feasibility at this margin level are declined at the ECI stage. This is a primary filter for the “Phantom Supply”, projects exist on paper, but they cannot afford the builder’s required margin, so they never commence.
- Infrastructure: Competition for resources from the “Big Build” allows civil contractors to command the highest margins. This sets a “floor” for labour pricing that the residential sector must match to attract trades, further inflating residential costs.
The Role of Subcontractor Risk Pricing
The margin expansion is not limited to the Head Contractor. Subcontractors, having witnessed the collapse of Head Contractors, are now pricing counterparty risk into their bids. A plumber bidding to a Tier 2 builder might add a 5-10% premium solely to cover the risk that the builder goes bust before final payment. This “Risk Cascade” flows up the chain, compounding the final cost to the developer.
Validating the “Phantom Supply” Hypothesis
The research provides robust validation for the “Phantom Supply” hypothesis: that Building Approvals are a misleading indicator of market health and that actual commencements are collapsing due to the “RiskLock.” While approvals in some jurisdictions show stability or even growth, the conversion rate from Approval to Commencement has deteriorated significantly, creating a growing backlog of “Stalled Stock.”
The Scale of Stalled Stock
Analysis of ABS and KPMG data reveals a massive accumulation of projects that have cleared the planning hurdles but failed to break ground.
- National Backlog: As of late 2023/early 2024, there were over 37,000 homes approved but not yet commenced across Australia. This figure represents a historical high in the disparity between the planning pipeline and the construction pipeline.
- The “Valley of Death”: The gap between approval and commencement, the “Valley of Death”, has widened. Projects approved in 2023 were feasibly modelled on 2023 costs and interest rates. By late 2025, with construction costs in key markets rising by another 5.0-5.5% and interest rates remaining restrictive, these projects are no longer bankable. They remain on the “Approved” list, creating the illusion of supply, but they are economically dead.
Brisbane: The Olympic Distortion
Brisbane represents the most acute example of the “Phantom Supply” dynamic, driven by the distorting gravity of the 2032 Olympic Games.
- Stalled Stock Increase: Brisbane recorded a 3.8% increase in stalled dwellings over the 12 months to Dec 2023.
- The “Crowding Out” Effect: The ramp-up of Olympic-related infrastructure (stadiums, transport) is absorbing the limited Tier 1 capacity in Queensland. RLB forecasts construction cost growth to pick up in Brisbane and the Gold Coast, specifically due to this activity.
- The Feasibility Crunch: Private residential developers in Brisbane are competing for the same labour pool as government-funded Olympic projects. The government can afford to pay union EBA rates; private developers cannot. This renders high-density residential projects unfeasible, leaving them stalled in the pipeline despite high demand for housing.
Perth: The Capacity Ceiling
Perth’s stagnation is driven by a different mechanism: a physical “Capacity Ceiling” imposed by the resources sector.
- Data Trends: Approvals in Western Australia dropped 5.1% in September 2025, the weakest month since October 2024. While the stalled stock numbers are described as “stable”, this stability masks a critical failure to launch new projects.
- Resource Competition: The mining and renewables sectors are absorbing the electrical and civil trades. High construction cost escalation is forecast to remain high in Perth due to this competition.
- The Labour Drain: A residential builder in Perth cannot compete with the wage packages offered by mining companies. Consequently, even if a project is approved and financed, it often cannot commence because the labour force does not exist to build it. This is a supply-side constraint that no amount of planning reform can solve.
The Data Lag and Current Reality
The ABS data for September 2025 shows a 4.4% seasonally adjusted fall in dwelling commencements nationally. This decline is occurring despite a rise in approvals in some months (e.g., Nov 2025 saw a 15.2% rise in approvals).
This divergence is the “smoking gun” of the Phantom Supply.
- Approvals Line: Trending flat or slightly up (volatile).
- Commencements Line: Trending down.
- Interpretation: The gap between these two lines represents the “RiskLock.” It represents developers who want to build (hence the approval) but cannot build (hence no commencement) because they cannot secure a builder at a feasible price.
Table 2: Regional Stagnation Indicators
| Region | Stalled Stock Trend | 2026 Cost Forecast | Primary Driver of “RiskLock” |
|---|---|---|---|
| Brisbane | +3.8% Increase | +5.0% | Olympic Infrastructure “Crowding Out”. |
| Gold Coast | High | +5.5% | Tier 1 Scarcity & Insolvency Risk. |
| Perth | Stable (Capped) | +5.3% | Mining/Resource Sector Labour Drain. |
| Sydney | High (11k+ units) | +4.0% | Feasibility Gridlock & Finance Costs. |
| Melbourne | High (6k+ units) | +4.0% | Union/EBA Escalation & Policy Uncertainty. |
The Death of Fixed Price Lump Sum (FPLS)
The “RiskLock” is fundamentally a rejection of the traditional risk allocation model, specifically the Fixed Price Lump Sum (FPLS) contract (e.g., AS4300 unamended). For decades, FPLS was the industry standard, allowing developers to transfer price and time risk to the builder. In the post-2024 environment, FPLS is viewed by Tier 1 builders as a “suicide pact.”
- Toxic Allocation: Under FPLS, builders absorbed the risk of material escalation, supply chain delays, and often latent conditions. In an environment of 5%+ annual escalation and labour shortages, this model guarantees losses.
- Refusal to Sign: Consequently, the tender-refusal dynamic examined above is often, at its root, a refusal of the contract form itself. Builders are simply stating they will not bid on FPLS terms. If the developer insists on FPLS to satisfy their bank, the builder walks away.
The Rise of Early Contractor Involvement (ECI)
The research identifies Early Contractor Involvement (ECI) not merely as a trend, but as the essential mechanism for project viability in 2025/2026.
- Strategic Necessity: ECI is described as the “smartest move” and “certainty” in the current market. It involves engaging the builder during the design phase (often at Schematic Design) on a fee-for-service basis.
- The Mechanism of ECI:
- Early Engagement: The builder joins the team before the design is frozen.
- Value Engineering: The builder provides real-time pricing feedback, allowing the design to be adjusted to the budget, rather than pricing a finished design that exceeds the budget.
- De-risking: Long-lead items (lifts, switchboards) are ordered early. Subcontractors are locked in.
- Conversion: The contract only converts to a Construction Contract (often a Guaranteed Maximum Price or GMP) once the scope is 80-90% defined and de-risked.
The Hybrid Model: ECI-to-D&C
The dominant model emerging is the “ECI-to-D&C” hybrid. This allows the developer to get the benefits of early engagement while eventually locking in a price (the D&C sum) for the construction phase. However, this price is significantly higher than historical FPLS prices because it includes the “Risk Pricing” and “Margin Rebuild” identified in the Margin Rebuild analysis above.
Cost Plus and Management Contracting
For the most complex and high-risk projects (e.g., CBD refurbishments, heritage works, difficult sites), the market is seeing a resurgence of “Cost Plus” or “Construction Management” (CM) contracts.
- Risk Transfer: In these models, the developer pays the actual cost of trade packages plus a management fee to the builder. The developer retains the trade cost risk.
- Builder Preference: Builders prefer this for high-risk work as it guarantees their margin and protects them from trade price blowouts.
- Lender Friction: Banks dislike Cost Plus contracts because there is no “fixed price.” This creates friction in achieving financial close, further contributing to the “stalled stock” problem as developers struggle to align builder demands with lender requirements.
Table 3: The Contractual Hierarchy (2026)
| Contract Model | Market Status | Builder Preference | Why? |
|---|---|---|---|
| Fixed Price (Lump Sum) | Declining / Toxic | Low | High insolvency risk; inability to price volatility. |
| Design & Construct (D&C) | Strained | Low/Medium | Only accepted with significant risk premiums attached. |
| ECI (Early Contractor Inv.) | Dominant | High | De-risks scope; secures supply chain; builds trust. |
| Cost Plus / Management | Rising (Complex) | Very High | Transfers trade risk to the client; guarantees builder’s fee. |
The “Two-Speed” Economy: A Structural Bifurcation
The construction sector has effectively bifurcated into a “Two-Speed” economy, creating a distinct “haves” and “have-nots” dynamic that explains the Phantom Supply.
- Speed 1: The Public & Institutional Sector (The “Haves”)
- Drivers: Government infrastructure (Big Build), Defence, Health, and Data Centres.
- Characteristics: High margins, collaborative contracts (Alliance/ECI), rise-and-fall mechanisms, priority access to Tier 1 labour.
- Outlook: Robust growth. These projects will cannibalise resources from the private sector, driving up costs and reducing availability for everyone else.
- Speed 2: The Private Residential & Commercial Sector (The “Have-Nots”)
- Drivers: Private apartments, office, retail.
- Characteristics: Feasibility challenges, “RiskLock” blockades, difficulty securing finance, reliance on fixed-price legacy models.
- Outlook: Stagnation. This is where the “Phantom Supply” resides. Projects here will remain stalled until rents/prices rise enough to cover the new 8-10% builder margins.
The 2026 Cost Outlook: “Sanguine” but Elevated
WT Partnership describes the 2026 escalation outlook as “sanguine” (approx. 5.2% nationally), potentially the lowest since the pandemic. However, this terminology requires nuanced interpretation.
- Rate vs. Base: A 5% increase is “low” compared to the 15% spikes of 2022, but it is applied to a cost base that is already 30-40% higher than 2019. The rate of growth is slowing, but the level of cost is permanently elevated.
- Compounding Effect: A 5% rise in 2026 on top of a 5% rise in 2025 creates a compounding affordability crisis for developers whose revenue models (sales prices) are capped by borrowing capacity.
The Productivity “Ghost in the Machine”
A recurring theme in the research is the collapse of productivity. AS Estimation and RLB both highlight “low productivity” and “productivity drag” as key cost drivers.
- The Cause: High churn rates, dilution of skill due to rapid workforce expansion (apprentices vs. journeymen), and the complexity of modern compliance (safety, ESG).
- The Effect: Even if material prices flatline, the cost to build continues to rise because it takes more man-hours to deliver the same unit of work. This productivity crisis is the “ghost” haunting the feasibility models, keeping the “RiskLock” firmly in place.
Future Outlook: The 2027 Escalation Spike
Looking beyond the immediate “RiskLock,” the data suggests a potential resurgence of cost escalation in 2027.
- The Driver: The convergence of the Brisbane 2032 ramp-up with renewed activity cycles in Sydney and Melbourne.
- The Implication: Developers who “wait out” the current high costs, hoping for a crash, are likely to be disappointed. The “window” of 2026, while expensive, may be cheaper than the “wall” of 2027. This realisation may eventually force the clearing of the Phantom Supply, but only for those projects that can absorb the new margin structures.
Conclusion: RiskLock is Validated
The “RiskLock” hypothesis is VALIDATED. The divergence between approvals and commencements is not a statistical anomaly but a rational market response to unpriced risk. Tier 1 builders, empowered by a surplus of public sector work, have successfully rebuilt their leverage. They are enforcing a “Risk Blockade” that filters out projects with inadequate margins (below 8-10%) or adversarial risk profiles (Fixed Price).
The “Phantom Supply” is real and growing. It represents a backlog of projects that are approved under the “old” economic model but are unbuildable under the “new” RiskLock model.
- CONSTRUCTION MARKET UPDATE – RLB, accessed January 2026, https://www.rlb.com/wp-content/uploads/sites/1/2025/12/RLB-Australia-Market-Intelligence-Update_Q4-2025.pdf
- Australian Construction Cost Trends & Forecasts 2026–2027, accessed January 2026, https://asestimation.com/blogs/australian-construction-cost-trends-forecasts-2026-2027/
- Construction Profit Margins in 2025: Benchmarks, Pressures, and What You Can Control, accessed January 2026, https://gobridgit.com/blog/profit-margin-in-construction/
- APB+SORCI+Report+2025+(White).pdf – AWS, accessed January 2026, https://publicsharedfiles.s3.ap-southeast-2.amazonaws.com/APB+SORCI+Report+2025+(White).pdf
- Almost 40,000 homes across Australia waiting to be built as interest …, accessed January 2026, https://www.theguardian.com/australia-news/article/2024/may/28/house-construction-lagging-behind-planning-approval-australia-interest-rates-building-costs
- 2025–2026 SEQ Construction Outlook: What’s next (and how to stay …, accessed January 2026, https://fara.au/blog/fy2526-seq-construction-outlook/
- Converging early contractor involvement (ECI) and lean construction practices for productivity enhancement | Request PDF – ResearchGate, accessed January 2026, https://www.researchgate.net/publication/281689391_Converging_early_contractor_involvement_ECI_and_lean_construction_practices_for_productivity_enhancement
- Subcontractor Engagement in the Two-Stage Early Contractor Involvement Paradigm for Commercial Construction – MDPI, accessed January 2026, https://www.mdpi.com/2673-9585/4/2/17
- 2026 Construction Industry Forecast | Glass Magazine, accessed January 2026, https://www.glassmagazine.com/article/2026-construction-industry-forecast
- 2026 Construction Industry Outlook: Demand Shifts, Rising Uncertainty – AGC News, accessed January 2026, https://news.agc.org/economics/2026-construction-industry-outlook/
- A Quick Take: The Construction Insurance Market, 2025-2026, accessed January 2026, https://axaxl.com/fast-fast-forward/articles/a-quick-take_the-construction-insurance-market_2025_2026
- Australian Construction Market Conditions Report – WT Partnership, accessed January 2026, https://wtpartnership.com.au/wp-content/uploads/2025/11/WT-November-2025-Australian-Construction-Market-Conditions-Report.pdf
- Construction cost escalation to remain elevated in 2026 – RLB | Oceania, accessed January 2026, https://www.rlb.com/oceania/insight/construction-cost-escalation-to-remain-elevated-in-2026/
- Australia’s construction costs to surge from 2027 – Build Australia, accessed January 2026, https://www.buildaustralia.com.au/news_article/australias-construction-costs-surge-from-2027/
- Media Release – Master Builders WA, accessed January 2026, https://www.mbawa.com/wp-content/uploads/2025/11/2025.11.03-WAs-building-approvals-numbers-sink-further.pdf
- Building Activity, Australia, June 2025 | Australian Bureau of Statistics, accessed January 2026, https://www.abs.gov.au/statistics/industry/building-and-construction/building-activity-australia/latest-release
- Building Approvals, Australia, November 2025 – Australian Bureau of Statistics, accessed January 2026, https://www.abs.gov.au/statistics/industry/building-and-construction/building-approvals-australia/latest-release
- Relational contracting in Nordic construction – a comparative longitudinal account of institutional field developments, accessed January 2026, https://research.chalmers.se/publication/541246/file/541246_Fulltext.pdf
- High construction costs top the list of concerns for Australian property lenders – CBRE, accessed January 2026, https://www.theaseandeveloper.com/news/2025/12/02/high-construction-costs-top-list-concerns-australian-property-lenders-cbre
- Early Contractor Involvement (ECI) for Facilities Management | CBC Group, accessed January 2026, https://www.cbcgroup.com.au/news/insights-hub/eci-a-strategic-approach-to-facilities-management
- Commercial Property Market Update – June 2025 – KPMG agentic corporate services, accessed January 2026, https://assets.kpmg.com/content/dam/kpmgsites/au/pdf/2025/commercial-property-market-update-june-2025.pdf