Half as Many Dwellings per Construction Worker Since 1995: Fewer Homes per Worker, or More Work per Home?
Construction Productivity (21239) −0.5400σ 2024–25 · position 14.7, ranked against 35 years
Scope and Purpose
NAB’s chief economist told the Senate Select Committee on Intergenerational Housing Inequity on 3 September 2026 that the Productivity Commission estimates “around 50 per cent fewer dwellings are produced per hour worked than was the case in the mid-1990s” (Dr Sally Auld, opening statement). The ABS does not publish dwellings per hour, but it publishes the pieces for a close version: dwellings completed per construction worker. In calendar 2025 there were 12.9 dwellings completed for every 100 people employed in construction, against 26.3 in 1995, a fall of 51%. The mechanism examined is where the difference went. The balance of the evidence is consistent with most of it being more real work in each dwelling, not much less work by each worker: real residential work per dwelling completed rose 88%, while real residential work per construction worker fell 8%.
The Evidence
Between 1995 and 2025 employment in construction rose from 598,000 to 1,345,000, or 125%, in the ABS Labour Force survey. Dwelling completions rose 10%, from 157,282 to 173,228. The ABS measure of the real value of residential building work done, in chain volume terms, rose 107%, from $50.8 billion to $105.3 billion. Work grew about as fast as the workforce and about ten times as fast as the number of dwellings.
Construction Employment, Real Residential Work Done and Dwellings Completed, Index 1995 = 100
APN calculation based on Australian Bureau of Statistics data: Labour Force, Australia, Detailed; Building Activity; Construction Work Done, calendar years 1995 to 2025. Each series is indexed to 1995 = 100. Employment is the average of the four quarterly (original) estimates; completions and chain volume work done are calendar-year sums.
Dividing the real work by the dwellings completed gives $323,000 of real residential work per dwelling in 1995 and $608,000 in 2025, 88% more. Looking at new residential building alone gives $273,000 and $522,000, 91% more, so alterations and additions explain little of it: they were 15.7% of residential work in 1995 and 14.1% in 2025. Dividing the real work by the workforce gives $85,000 per construction worker in 1995 and $78,000 in 2025, a fall of 8%; the series is volatile, ranging from $74,000 to $101,000, with highs in 2002 ($101,000) and 2016 ($100,000); 2025 is 22% below 2016.
Dwellings, Work and Workers, Selected Calendar Years
| Year | Employed in construction | Dwellings completed | Dwellings per 100 workers | Real residential work per dwelling ($’000) | Real residential work per worker ($’000) |
|---|---|---|---|---|---|
| 1995 | 598,364 | 157,282 | 26.3 | 323 | 85.0 |
| 2005 | 843,052 | 165,351 | 19.6 | 457 | 89.7 |
| 2015 | 1,029,040 | 197,253 | 19.2 | 494 | 94.7 |
| 2019 | 1,168,811 | 202,467 | 17.3 | 499 | 86.5 |
| 2025 | 1,345,273 | 173,228 | 12.9 | 608 | 78.3 |
APN calculation based on Australian Bureau of Statistics data: Labour Force, Australia, Detailed; Building Activity; Construction Work Done, calendar years. Work done is chain volume, total sectors, original, all residential building including alterations and additions.
The ABS productivity estimates point the same way but are smaller. Construction labour productivity, gross value added per hour worked, was 11% higher in 2024–25 than in 1994–95, against 64% for the market sector as a whole, and 19% lower than its peak in 2013–14 (ABS, Estimates of Industry Multifactor Productivity). Construction Productivity (21239) reads −0.5400σ for 2024–25, the seventh consecutive annual decline. So output per worker has stopped rising and has fallen since 2014, but it has not fallen by half.
What the Diagnosis Does Not Show
The extra work in each dwelling is not decomposed here. Chain volume work per dwelling can rise through larger dwellings, a shift from houses to apartments and townhouses, which take more work per dwelling, higher specification and compliance, or a deflator that understates cost increases and so overstates real work. The ABS series cannot separate these, so the diagnosis rests on the size of the effect and not on its cause. Employment in construction is not all in housing. Employment in building construction rose 116%, heavy and civil engineering 137%, and construction services (the trades) 126%, from 380,000 to 860,000, so the workforce serves non-residential building and engineering work as well as dwellings; the fall in residential work per worker partly reflects that. Engineering work is not measured here. Hours are not measured. NAB’s statement is per hour worked, and this test is per person employed; average hours per worker may have changed over thirty years.
The Test
The diagnosis can be tested by the ABS productivity release for 2025–26, due about February 2027, and by the next four quarters of Building Activity and Construction Work Done. If real residential work per dwelling completed stays near $600,000 while completions rise, completions per worker will recover only slowly, and the mechanism is as described. If construction value added per hour keeps falling while real work per dwelling does not, the larger part of the shortfall is in the workforce, and the mechanism is wrong in size. The ABS 2026 Census, with first results in June 2027, will give the occupation and industry counts to check the split of the workforce between housing and other work.
This diagnosis speaks only to the structural conditions the cited data can independently support; it does not constitute a forecast of construction costs, housing supply or government policy, and no such view is expressed or implied.
What Would Show Which Way It Is Going
Signposts
| Signpost | Next release | What it would show |
|---|---|---|
| ABS Estimates of Industry Multifactor Productivity, 2025–26 | About February 2027 | Whether construction value added per hour stays below its 2013–14 level |
| ABS Building Activity, September quarter 2026 | 13 January 2027 | Whether completions rise while real work per dwelling holds |
| ABS Labour Force, Australia (the Detailed release ceased with March 2026) | 19 November 2026 (October 2026 issue) | Whether construction employment keeps rising while completions are flat, once industry tables are published under the new release plan |
Release dates from the ABS calendar where stated.
APN Analytical Synthesis
The fall of 51% in dwellings per construction worker is real as arithmetic and is mostly a change in what a dwelling is. Each completed dwelling embodied 88% more real work in 2025 than in 1995, and real residential work per worker fell 8%, and 22% since 2016. That is a smaller productivity problem than the dwelling count suggests and still a problem: Construction Productivity (21239) has fallen for seven consecutive years. The next data to test the argument are the ABS productivity release due about February 2027 and the September quarter Building Activity release.
This diagnosis speaks only to the structural conditions the cited data can independently support; it does not constitute a forecast of construction costs, housing supply or government policy, and no such view is expressed or implied.
- Australian Bureau of Statistics (Reference period: 2024-25) Estimates of Industry Multifactor Productivity [https://www.abs.gov.au/statistics/industry/industry-overview/estimates-industry-multifactor-productivity/latest-release], ABS Website, accessed 8 November 2026.
- Australian Bureau of Statistics (Reference period: February 2026) ‘Employed persons by industry division and by industry sub-division of main job, original (Tables 04 and 06)’ [data set], Labour Force, Australia, Detailed (final issue; the release has ceased) [https://www.abs.gov.au/statistics/labour/employment-and-unemployment/labour-force-australia-detailed/latest-release], accessed 8 November 2026.
- Australian Bureau of Statistics (Reference period: June quarter 2026) ‘Number of dwelling unit completions by sector, original (Table 37)’ [data set], Building Activity, Australia [https://www.abs.gov.au/statistics/industry/building-and-construction/building-activity-australia/latest-release], accessed 8 November 2026.
- Australian Bureau of Statistics (Reference period: June quarter 2026) ‘Value of work done, chain volume measures, original (Table 3)’ [data set], Construction Work Done, Australia, Preliminary [https://www.abs.gov.au/statistics/industry/building-and-construction/construction-work-done-australia-preliminary/latest-release], accessed 8 November 2026.
- National Australia Bank NAB Chief Economist opening statement to Senate Select Committee (Dr Sally Auld, 3 September 2026) [https://www.nab.com.au/news/economy-markets/nab-chief-economist-opening-statement-to-senate-select-committee], accessed 31 October 2026.
ABS material is used under a Creative Commons Attribution 4.0 International licence. Calculations are APN’s and are not attributable to the ABS.
NAB’s statement is quoted and attributed; the publication remains the property of the publisher.
Disclaimer
The analysis and information contained in this publication are for general informational and strategic purposes only and do not constitute financial, investment, legal, or any other form of professional advice. Australian Property Network is not a licensed financial advisor. Property values and market conditions can go up or down. Before making any property or investment decisions, you must conduct your own thorough research and seek independent professional advice tailored to your specific circumstances. Images are for illustrative purposes only. E.&O.E.