How the Housing Development Readings Are Measured: Price, Land, Costs, Public Works and Finance

APN Codex · Future Development Pipeline (24400) DistillationEL 2 · Foundational

How the Housing Development Readings Are Measured: Price, Land, Costs, Public Works and Finance

Reference: A-261127-C24400.2 · Published 27 November 2026 · Data to the June quarter 2026
Written for readers who want to know how each reading is measured.

A reading is only as good as the way it is built. This page explains how APN measures each of the five things that decide whether housing projects proceed, which official figures go in, how each is turned into a reading that can be compared across time, and why one of them is turned upside down before the five are averaged. It assumes you have read the plain-English tier, and it explains each method word as it arrives.

1Reading a figure against its own history

Every reading on this page follows the same three steps. First, APN takes an official figure that is published every quarter, such as the growth in what builders pay for materials. Second, it compares that figure with its own record, using the fifteen years from 2011 to 2025 as the yardstick. The yardstick has two parts: the average of the figure over those years, and the standard deviation, which is the usual size of its movements around that average. Third, it reports how far the latest figure sits from the average, counted in standard deviations. A reading of zero means the figure is at its average, a reading of plus one means it is one standard deviation above, and minus one means one below.

Standardising does something useful. A rate of 4 per cent and a ratio of 0.71 cannot be set side by side, but readings of minus 0.12 and minus 2.40 can, because each says how unusual the figure is against its own history. It does not say whether the figure is good or bad, and it does not say what will happen next.

A reading has a second companion, the position. The position says where the latest reading ranks among all the quarters on record: it is the share of the other quarters that were lower. A position of 73.7 means the latest quarter was higher than 74 per cent of the other quarters of its record. Every position on this page is published with the number of quarters it was ranked against, because a position over 12 quarters and one over 60 are not equally informative.

The five readings are the APN Residual Land Value (RLV) Gap™, the APN Enabling Infrastructure Index™, the APN Supply Chain Strain Index™, the APN Replacement Cost Gap™ and the APN Development Finance Conditions™. A sixth component, APN Social Licence & Objection Velocity™ (24440), does not yet compose into the index. Each is described below with its official sources. All data run to the June quarter 2026, the latest quarter for which all five are complete.

2Measuring the room between price and building cost

The APN Residual Land Value (RLV) Gap™ (24410) starts with a simple question: after a typical new home is paid for, how much of a typical home’s price is left, compared with what the land is worth? It uses three figures, all from the Australian Bureau of Statistics (ABS).

The first is the average price of a home, from the ABS Total Value of Dwellings, which was $1,100,400 in the June quarter 2026. The second is the average building cost of a new dwelling. The ABS Building Approvals release counts the dwellings that councils approve, the official permit that allows construction to begin, and the value of the building work approved. Dividing the value by the number over the latest four quarters gives about $549,500 for each new dwelling. The third is the value of the land under an average home, which is the value of the land that households own (from the ABS Australian National Accounts: Finance and Wealth) divided by the number of homes. That came to about $780,200.

Subtracting the building cost from the price leaves about $550,900. Divided by the land value, that is $0.71 for each $1 of land value. A year earlier it was $0.73. Against the yardstick, whose average is 0.79 and standard deviation 0.03, the latest figure is minus 2.40 standard deviations, a position of 0.0: no quarter of the 60 on record was lower.

The ratio has two features worth knowing. It is built from averages, so it describes the country, not a project. And it mixes a stock with a flow: the price and the land cover every home, mostly existing ones, while the cost covers only the new homes approved in the latest four quarters. The ratio therefore has no pass mark. A figure of 0.71 does not mean a project fails; it is the movement against the ratio’s own history that the reading follows. The chart below shows the ratio each quarter, divided into the phases in which the room widened and narrowed.

The room between price and building cost, with its phases
Average home price less the average cost of a new dwelling, divided by the value of land per home, dollars per $1 of land value, September quarter 2011 to June quarter 2026.

Gold line: dollars left for each $1 of land value. Gold bands: phases in which the room widened; slate bands: phases in which it narrowed. The turning points are the quarters of highest and lowest value between them: $0.75 (September quarter 2012), $0.84 (June quarter 2015), $0.76 (June quarter 2019) and $0.86 (December quarter 2021). The latest quarter, $0.71, is the lowest of the record. Sources: Australian Bureau of Statistics, Total Value of Dwellings, Building Approvals and Australian National Accounts: Finance and Wealth.

3Measuring costs, workers and the replacement cost gap

Two readings follow costs. The APN Supply Chain Strain Index™ (24430) combines three measures in fixed shares. Forty per cent is the growth over the year in the prices builders pay for materials, from the ABS Producer Price Index for input to house construction, which follows the materials and other inputs that builders buy. Thirty per cent is how many dwellings are being approved for each $1 million of residential building work done, a measure of whether approvals are arriving faster than the industry can work through them. The last thirty per cent is the construction job vacancy rate: vacancies counted by the ABS Job Vacancies Survey on a single day each February, May, August and November, as a share of filled construction jobs.

In the June quarter 2026 the three stood at 3.8 per cent growth in input prices, 1.80 dwellings approved for each $1 million of work, and 1.48 vacancies for every 100 filled jobs. Each was converted to a standard-deviation reading, and the weighted sum is the strain reading of minus 0.26. Vacancies were 3.27 for every 100 jobs in the June quarter 2022, the highest of the record charted here.

The APN Replacement Cost Gap™ (24450) compares two growth rates. It takes the growth over the year in the average home price (6.8 per cent to the June quarter 2026) and subtracts the growth in builders’ input prices (3.8 per cent), after converting each to a reading against its own record. The price growth reads 0.15 and the input growth 0.07, so the gap is 0.08. That gap is itself measured against its own record, which gives the reading of 0.11. Home prices include land, so the gap mostly tracks land value. The chart below shows the two growth rates. Home prices rose faster than input prices through 2020 and 2021, reaching 24.1 per cent in the year to the December quarter 2021, and input prices rose faster in 2022, reaching 17.3 per cent in the year to the June quarter 2022, which turned the gap negative for a time.

Home prices against builders’ input prices, change over the year
Growth over the year in the average home price and in the input price index for house construction, per cent, September quarter 2012 to June quarter 2026.
Home price growthBuilders’ input price growth

Gold line: the average home price. Slate line: the ABS input price index for house construction. Dashed line: zero growth. Home prices peaked at 24.1 per cent (December quarter 2021) and input prices at 17.3 per cent (June quarter 2022). The latest quarter reads 6.8 and 3.8 per cent. Sources: Australian Bureau of Statistics, Total Value of Dwellings; Producer Price Indexes, Australia.

4Measuring public works and finance

Public works come next. The APN Enabling Infrastructure Index™ (24420) follows the value of engineering construction work done for the public sector on roads, water, sewerage and electricity. The ABS Engineering Construction Activity release reports work done for the public and private sectors, and APN adds the four public-sector types of work. The ABS reports these four types of public-sector work within its engineering construction series. The measure is the growth over the year in the dollar value of that work, in dollars as spent and not adjusted for rising prices. In the June quarter 2026 it was 4.3 per cent, a reading of minus 0.12, a position of 43.9 among 156 quarters. The record begins in September 1987, the longest of the five.

Finance is the fifth reading, and it has two parts of equal weight. The first is the limits that banks and other deposit-taking institutions set on lending to land development and subdivisions, from the Australian Prudential Regulation Authority (APRA) Quarterly ADI Property Exposures statistics. A limit is the amount made available, not the amount drawn, and APRA reports limits as amounts made available. The second is the value of new loans that businesses took out for construction, from the ABS Lending Indicators, which publish new borrower-accepted loan commitments for businesses by purpose, including construction. Both are measured as growth over the year.

The two behave very differently, as the chart below shows. Lender limits move in long swings, with growth of 25.2 per cent in the year to the June quarter 2026 and a peak of 31.9 per cent in the year to the December quarter 2015. Construction loan commitments swing sharply from quarter to quarter, because a few large commercial loans can dominate a single quarter: growth was 102.9 per cent in the year to the December quarter 2012, minus 43.0 per cent in the year to the December quarter 2020, 55.3 per cent in the year to the March quarter 2026 and 0.1 per cent in the year to the June quarter 2026. Against the yardstick, the standard deviation of the limits growth is 13.5 points and that of the loans growth 32.6; the loans growth is given the same weight, so the larger swings carry through into the reading unless the limits move the other way.

Lender limits and construction loans, change over the year
Growth over the year in lender limits for land development and in new business loan commitments for construction, per cent, March quarter 2012 to June quarter 2026.
Lender limitsConstruction loan commitments

Gold line: limits that banks and other deposit-taking institutions set for lending to land development and subdivisions. Slate line: new loan commitments for fixed-term business construction loans, original. Dashed line: zero growth. A limit is the amount made available, not the amount drawn. Sources: Australian Prudential Regulation Authority, Quarterly ADI Property Exposures; Australian Bureau of Statistics, Lending Indicators.

The finance reading in the June quarter 2026 is 0.62, a position of 73.7 among 58 quarters. In the March quarter 2026 it was at the highest of its record.

5Ranking a reading: the position

The position is simple to compute. Take the quarters on a reading’s record, count how many were lower than the latest, and divide by the number of other quarters. The lowest quarter reads 0.0 and the highest 100.0. For the room between price and building cost, none of the other 59 quarters was lower, so the position is 0.0. For the finance reading, 42 of the other 57 were lower, a position of 73.7. For public works, 68 of the other 155, a position of 43.9; for strain, 25 of the other 59, 42.4; for the replacement cost gap, 20 of the other 55, 36.4.

The five records are not the same length. Public works run back to 1987 and the others begin between 2011 and 2012, so a position near the middle means something different for the longest record than for the shortest. That is why each position carries its count. The chart below ranks the five, with the combined index described in the next section.

Where each reading ranks on its own record
Position of the latest reading, June quarter 2026: the share of the other quarters of its record that were lower, out of 100.

Bars from zero. Slate bar: the combined index (higher means more friction). Gold bars: the five readings as measured, before any flipping. Number of quarters ranked: combined index 56, Development Finance 58, Enabling Infrastructure 156, Supply Chain Strain 60, Replacement Cost Gap 56, Residual Land Value Gap 60.

6Putting the five together, and why four are flipped

The APN Future Development Pipeline Index™ (24400) averages the five readings with equal weights of 20 per cent. There is one adjustment. For four of the five, a higher reading means less friction in delivering new housing: more room between price and cost, more public works, a wider gap between price growth and cost growth, and more finance available. For the strain reading, a higher figure means more friction, because it measures the cost of materials, the scarcity of workers and the backlog of approvals. To average readings that point in opposite directions, APN flips the four. A reading of minus 2.40 for the room between price and cost then enters the average as plus 2.40, a contribution of plus 0.48 once weighted.

The result is an index in which a higher reading means more friction. In the June quarter 2026 it was 0.31, a position of 83.6 among 56 quarters, higher than in 46 of the other 55 and the highest since the June quarter 2023.

The chart below shows how the five contributed in the June quarter 2026. The room between price and building cost contributed 0.48, public works 0.02, strain minus 0.05, the replacement cost gap minus 0.02 and finance minus 0.12. A bar to the right adds friction and a bar to the left subtracts it. One reading, the narrowest room between price and cost on record, supplies more than the whole of the index: the other four together subtract.

What each reading added to the combined index in the June quarter 2026
Weighted contribution of each reading to the combined index, in standard deviations, after flipping the four readings for which a higher figure means less friction.

Gold bars to the right add friction; slate bars to the left subtract it. Contributions sum to the index, 0.31. Each is 20 per cent of the reading, with the four flipped.

Two limits belong with the method. Materials prices feed two of the five readings, the strain reading and the replacement cost gap, so input costs carry more than one reading’s share. And the index describes national conditions. A project, a site or a state can sit far from them. The replacement cost gap uses the ABS input price index for house construction; a different cost measure would give a different reading. The next tier of this series explains how the readings are used.