Why New Homes Get Built or Stall: Land, Building Costs, Public Works and Finance

APN Codex · Future Development Pipeline (24400) DistillationEL 1 · Plain English

Why New Homes Get Built or Stall: Land, Building Costs, Public Works and Finance

Reference: A-261124-C24400.1 · Published 24 November 2026 · Data to the June quarter 2026
Written for the general reader. No prior knowledge assumed.

Australia needs new homes, but whether a particular project goes ahead depends on sums that the buyer never sees. The finished home has to sell for more than the land, the building work, the roads and pipes that serve it, and the borrowed money that pays for them all. This page explains, in everyday words, the five things that decide whether housing projects proceed or stall, how each stood in the June quarter 2026, and how APN reads them together.

1Five things that decide whether a project proceeds

A developer or a builder starting a project is, in effect, doing one long subtraction. The expected sale price of the finished homes comes first. Out of it come the cost of the land, the cost of the building work, the cost of connecting the homes to roads, water, sewers and power, the cost of borrowing, and a return for the risk taken. If anything is left, the project can go ahead. If nothing is, it waits, shrinks or stops.

That gives five things to watch, and APN follows one reading for each. The first is how much room the price of a home leaves after the cost of building it, measured against the value of the land. The second is the public works that make land usable, such as roads, water, sewerage and electricity. The third is strain on supply chains: the cost of materials, the availability of construction workers, and how fast approvals are being turned into building work. The fourth is the gap between what homes sell for and what it would cost to replace them. The fifth is the finance that lenders make available to developers.

None of these on its own says whether homes will be built. Read together, they show where the friction is. On this page, friction means anything that makes it harder or slower to deliver new housing.

2Land value against the cost of building

The most direct test of whether a project makes sense is to compare what is left of a home’s price once building is paid for with what the land is worth. The Australian Bureau of Statistics (ABS) publishes the average price of homes every quarter. It also publishes the value of the dwellings that councils approve for new construction, and the value of the land that households own. Land is about 74 per cent of the value of households’ residential land and dwellings (ABS household balance sheet, Australian National Accounts: Finance and Wealth).

From these, APN works out, for each $1 of land value, how much of an average home’s price is left after taking off the average cost of a new dwelling. In the June quarter 2026 the answer was $0.71. A year earlier it was $0.73, and at its highest, in the December quarter 2021, it was $0.86. The June 2026 figure is the lowest of the 60 quarters on the record, which begins in the September quarter 2011, and the March quarter 2026 was the second lowest, at $0.72.

This is a comparison of averages, and it is approximate. The price and the land value describe the whole stock of homes, mostly existing ones, while the building cost describes homes approved for construction in the latest four quarters. The level has no pass mark. What matters is how it moves against its own history, and on that record the room between price and building cost is at its narrowest. The chart below shows each quarter.

What is left of an average home’s price after building, for each $1 of land value
Average home price less the average cost of a new dwelling, divided by the value of the land under an average home, each quarter from September 2011 to June 2026, dollars per $1 of land value.

Gold line: dollars left for each $1 of land value. Lowest $0.71 (June quarter 2026, the latest); second lowest $0.72 (March quarter 2026); highest $0.86 (December quarter 2021). The level has no pass mark: its movement against its own history is what counts. Price and land describe the whole stock of homes; the building cost describes homes approved in the latest four quarters. Sources: Australian Bureau of Statistics, Total Value of Dwellings (June quarter 2026), Building Approvals (dwelling units and value approved, new residential buildings) and Australian National Accounts: Finance and Wealth (household residential land and dwellings).

Think of it like this…

Picture one average home and one new build:

  • The average home was worth $1,100,400 in the June quarter 2026.
  • Over the latest four quarters, councils approved new dwellings worth about $549,500 each on average.
  • Taking that off the price leaves about $550,900.
  • The land under an average home is worth about $780,200 (APN’s calculation from the ABS household balance sheet and the number of homes implied by ABS Total Value of Dwellings). So the $550,900 left is $0.71 for each $1 of land value. A year earlier the figure was $0.73.

These are averages. The price and the land value cover every home in the country, mostly existing ones, while the building cost covers new homes only; a particular project could sit far above or below these figures, and what a builder or developer actually pays depends on the site, the design, the state and the lender.

3What materials and workers cost

Building costs reach a project through materials and labour. The ABS Producer Price Indexes follow what builders pay for materials, and its index of input prices for house construction rose 3.8 per cent over the year to the June quarter 2026. That is faster than in 2024 and early 2025, when growth slowed to 1.1 per cent in the year to the March quarter 2025, but far below the 17.3 per cent of the year to the June quarter 2022, the highest of the quarters charted from March 2011. The chart below shows each quarter.

The second part of strain is people. The ABS counts job vacancies in construction, and APN divides them by the number of filled jobs in the industry. In the June quarter 2026 there were 1.48 vacancies for every 100 filled construction jobs, against 3.27 in the June quarter 2022. The vacancies are from ABS Job Vacancies, and the filled jobs from the ABS Labour Account.

The replacement cost gap compares two rates of growth. Over the year to the June quarter 2026 the average home price rose 6.8 per cent, while the input prices builders pay rose 3.8 per cent. In the year to the June quarter 2026, home prices therefore rose faster than building materials. The average price includes the land under the home, so this gap mostly tracks land value, not the cost of bricks and timber.

Prices builders pay for materials, change over the year
ABS Producer Price Index, input to house construction, weighted average of six capital cities, growth over the year to each quarter from March 2011 to June 2026, per cent.

Gold line: growth over the year in the prices builders pay for materials. Highest 17.3 per cent (year to the June quarter 2022); lowest since then 1.1 per cent (year to the March quarter 2025); latest 3.8 per cent (year to the June quarter 2026). Source: Australian Bureau of Statistics, Producer Price Indexes, Australia, input to the house construction industry (Table 18).

4Public works and the money to build

Land cannot be built on until it is connected. The ABS measures the value of engineering work done for the public sector, and APN follows the part spent on roads, water, sewerage and electricity. In the June quarter 2026 that work was worth $12.97 billion, 4.3 per cent more than a year earlier. The growth was 41.4 per cent in the year to the March quarter 2022, the highest of the quarters charted from March 2011. The figures are in dollars as spent and are not adjusted for rising prices, so part of the growth reflects higher prices.

Finance is the fifth thing. The Australian Prudential Regulation Authority (APRA) publishes the limits that banks and other deposit-taking institutions have set for lending to land development and subdivisions. A limit is the amount made available, not the amount drawn. These limits stood at $36.4 billion in the June quarter 2026, 25.2 per cent more than a year earlier, up from $29.1 billion.

A second measure of finance, the value of new loans that businesses took out for construction, is much more erratic. The ABS Lending Indicators (new business loan commitments for fixed-term construction loans, original) report it was $13.6 billion in the June quarter 2026, only 0.1 per cent more than a year earlier, after a rise of 55.3 per cent in the year to the March quarter 2026. Large commercial loans make single quarters lumpy, which is why APN reads the two measures together. The charts below show the public works and lender limits measures each quarter.

Public works on roads, water, sewerage and electricity, change over the year
Value of engineering construction work done for the public sector on roads, water, sewerage and electricity, growth over the year to each quarter from March 2011 to June 2026, per cent.

Gold line: growth over the year in the dollar value of the work. Dashed line: zero, where the work is worth the same as a year earlier. Highest of the quarters charted 41.4 per cent (year to the March quarter 2022); lowest minus 23.4 per cent (year to the September quarter 2014); latest 4.3 per cent (year to the June quarter 2026). Dollars as spent, not adjusted for rising prices. Source: Australian Bureau of Statistics, Engineering Construction Activity, Australia (Table 11, original).

Lender limits for land development, change over the year
Limits set by banks and other deposit-taking institutions for lending to land development and subdivisions, growth over the year to each quarter from March 2012 to June 2026, per cent.

Gold line: growth over the year in the limits. Dashed line: zero, where the limits are the same as a year earlier. Highest 31.9 per cent (year to the December quarter 2015); lowest minus 17.2 per cent (year to the March quarter 2012); latest 25.2 per cent (year to the June quarter 2026). A limit is the amount made available, not the amount drawn. Source: Australian Prudential Regulation Authority, Quarterly ADI Property Exposures (commercial property exposure limits, all ADIs).

5How APN keeps track

APN follows these questions through five readings, each compared with its own history. For each reading, the position is the share of the other quarters on its own record that were lower. In the June quarter 2026:

The APN Residual Land Value (RLV) Gap™ (24410) is the room between price and building cost, set against land value. No other quarter of the 59 on its record was lower, so its position is 0.0. The APN Enabling Infrastructure Index™ (24420) follows public engineering work on roads, water, sewerage and electricity. It was higher than in 68 of the other 155 quarters since September 1987, a position of 43.9. The APN Supply Chain Strain Index™ (24430) combines the cost of inputs, construction vacancies and the pace of approvals relative to work done. It was higher than in 25 of the other 59 quarters, a position of 42.4.

The APN Replacement Cost Gap™ (24450) follows how fast home prices are growing against construction input costs. It was higher than in 20 of the other 55 quarters, a position of 36.4. The APN Development Finance Conditions™ (24460) follows growth in lender limits for land development and in construction loans. It was higher than in 42 of the other 57 quarters, a position of 73.7. Building materials feed two of the five readings, the strain index and the replacement cost gap, so input costs count for more than one reading’s share.

The APN Future Development Pipeline Index™ (24400) puts the five together in equal parts. It points one way: a higher reading means more friction. For the strain index, a higher reading already means more friction. For the other four, a higher reading means less friction, so APN flips them before averaging. In the June quarter 2026 the index was higher than in 46 of the other 55 quarters since September 2012, a position of 83.6, the highest since the June quarter 2023.

Two moves explain the rise from the March quarter 2026. Development finance was at the highest of its record in March, and it eased in June. The replacement cost gap also narrowed. Both are flipped, so their easing adds friction. The room between price and building cost, already the lowest on the record, narrowed further, from $0.72 to $0.71 for each $1 of land value, and that adds friction as well.

6What this means for you

If you are a builder or developer: In the June quarter 2026 the room between an average home’s price and its building cost, against land value, was the lowest of 60 quarters, while material prices were rising by 3.8 per cent a year. Lender limits for land development were 25.2 per cent higher than a year earlier.

If you are buying a new home: Every project rests on the sums above, and the price of a new home has to cover them. The averages here describe the whole country, and the price of any one home depends on its land, its size, its location and its builder.

If you own a development site: The value of land sits on one side of the comparison, and land is about 74 per cent of the value of households’ residential land and dwellings (ABS household balance sheet). In the June quarter 2026 the average home price was 6.8 per cent higher than a year earlier.

If you rent: Rents depend on the number of homes available, and new homes add to that number. The friction reading describes how hard it is, nationally, to deliver them. A project that stalls is a home that is not added.

These are national averages. Your own project, site, state and lender can sit well above or below them.

In one sentence: housing projects proceed when a finished home sells for more than its land, building work, public works and finance cost, and in the June quarter 2026 the room between price and building cost was the lowest of a 60-quarter record while lender limits and public works spending grew, leaving APN’s friction reading at 83.6, its highest since the June quarter 2023.