How Long Does a New Home Take to Build? CEDA’s Build-Time Figures Tested Against the ABS Pipeline
Construction Completion Lag (21290) +2.0205σ June quarter 2026 · position 90.4, ranked against 84 quarters
Scope and Purpose
A 2026 report from CEDA, the Committee for Economic Development of Australia, written with Urbis by Danika Adams, Jonathon Mahon and Clinton Ostwald, argues that modern methods of construction (prefabrication and modular building) could cut build times and costs (CEDA, Built different: Modern methods of construction). It states that the average new standalone home takes 9.2 months to build and a new apartment building 2.4 years, and that modern methods “can reduce construction times by 20 to 50 per cent”, which it says would remove two to five months from a house build. The page does not state how the build times were derived. The Australian Bureau of Statistics counts the dwellings under construction and the dwellings completed each quarter, which gives an implied average. The house figure holds with a qualification: the ABS implies about ten months, 0.7 to 1.3 months longer than CEDA’s. The apartment figure is close to the recent high of the ABS series, which is for a broader category. The saving is arithmetic and cannot be tested.
How the Time to Build Is Measured Here
The ABS does not publish the average duration of a build. It does publish the number of dwellings under construction at the end of each quarter (Table 76) and the number completed in the quarter (Table 37), by type of building. If the pipeline is steady, the average time a dwelling spends under construction equals the number under construction divided by the number completed in a month. At the end of June 2026, 95,447 new houses were under construction and 108,956 were completed over the four quarters to June, or 9,080 a month: 10.5 months. For new other residential dwellings, 152,264 were under construction and 70,923 were completed, or 5,910 a month: 25.8 months, or 2.1 years. Using the average of the last five quarter-end stocks instead of the latest, which allows for a pipeline that has been growing, gives 9.9 months for houses and 24.8 months for other residential. The measure runs from commencement to completion: it excludes approval and pre-construction time, which CEDA’s page does not say it includes.
Proposition One: The Average New Standalone Home Takes 9.2 Months to Build
On the ABS counts, a new house took 10.5 months in the year to June 2026 (9.9 on the average stock). Over the two years to June 2026 the implied figure ranged from 9.0 to 10.5 months, so CEDA’s 9.2 sits at the low end of that range. Before 2020 the figure averaged 6.8 months and was about six months through 2019; it rose to 11.3 months in the March quarter 2023, the longest in the 102 quarters from March 2001, and the latest reading is the 10th longest of 102. The claim holds with a qualification: 9.2 months is within the range of the last two years, though a little below the current implied time. The longer time to build compared with before 2020 is the larger finding.
Implied Average Time to Build, New Houses and New Other Residential, Months, March 2001 to June 2026
APN calculation based on Australian Bureau of Statistics data: Building Activity, Australia, June quarter 2026, Tables 37 and 76, total sectors, new houses and new other residential, original. Months = dwellings under construction at the end of each quarter divided by completions a month, averaged over the four quarters to that date. Dotted lines mark CEDA’s 9.2 months (houses) and 2.4 years (apartment buildings), the latter shown as 28.8 months.
Proposition Two: A New Apartment Building Takes 2.4 Years
The ABS category is ‘total other residential’, which covers apartments but also townhouses, terraces and semi-detached dwellings, so it is broader than an apartment building. It implies 25.8 months (2.1 years) at June 2026 and 24.8 months on the average stock. The series peaked at 29.2 months in the September quarter 2022 and stood at 28.6 months in both the December 2025 and March 2026 quarters, so CEDA’s 2.4 years (28.8 months) matches those recent highs and is longer than the latest reading. Before 2020 the figure averaged 17 months. The claim holds with a qualification: it matches the high end of the recent ABS range for a broader category, and is above the latest reading. A fall in the quarter from 28.6 to 25.8 months comes from the June quarter completions of 19,638, the highest of the last five quarters.
Proposition Three: Modern Methods Could Remove Two to Five Months
CEDA says that a 20 to 50 per cent cut would take two to five months from a 9.2-month house build. The arithmetic holds: 20% of 9.2 months is 1.8 months and 50% is 4.6. On the ABS-implied 10.5 months the range would be 2.1 to 5.3 months. Whether modern methods deliver a 20 to 50 per cent saving at scale is a forecast, and the page gives no method for it. The ABS does not identify prefabricated or modular dwellings in Building Activity, so their share of completions cannot be measured here. The saving is not tested. The cost estimate, about 20 per cent at scale, is also not tested.
The Tests at a Glance
| CEDA statement | Test | Result |
|---|---|---|
| The average new standalone home takes 9.2 months to build | ABS dwellings under construction divided by monthly completions, new houses | Holds with qualification: 10.5 months now (9.9 on the average stock), 9.0 to 10.5 over two years; about 6 months before 2020 |
| A new apartment building takes 2.4 years | As above, new other residential (a broader category) | Holds with qualification: 2.1 years now, 2.4 years in the recent high |
| Modern methods could cut times by 20 to 50 per cent, or two to five months | Arithmetic on 9.2 months | Arithmetic holds; the saving is not testable from the ABS |
Sources: CEDA, Built different: Modern methods of construction, 2026; ABS Building Activity, Australia, June quarter 2026, Tables 37 and 76; APN calculation.
Not Tested
CEDA’s page gives no publication date, no method for the 9.2 months or 2.4 years, and no source for the share of homes built with modern methods. The report itself was not read beyond its published summary. The cost figures, including the $116,000 saving per apartment, are CEDA’s estimates and are not tested.
What Would Show Which Way It Is Going
Signposts
| Signpost | Next release | What it would show |
|---|---|---|
| ABS Building Activity, September quarter 2026 | 13 January 2027 | Whether the implied time to build a house keeps lengthening while other residential keeps shortening |
| ABS Building Approvals | Monthly | The approvals that feed the pipeline |
| NSW modern methods of construction framework | Not announced | Whether recognition in law changes the share of homes built off site |
Release dates from the ABS calendar where stated.
APN Analytical Synthesis
CEDA’s starting point is close to the ABS counts: a new house now takes about ten months from commencement to completion, and an apartment or townhouse about two years. The larger finding in the ABS counts is the lengthening, from about 7 months for a house before 2020 to between nine and eleven months since 2022, which is the case a faster method of building would have to answer. Construction Completion Lag (21290) reads +2.0205σ at the June quarter 2026 for the same reason: the whole pipeline of 248,733 dwellings under construction is 15.7 months of completions, against a June-quarter average of 9.3 months since 1984. Whether prefabrication shortens it is the next data point to watch, and the ABS would need to report the method of construction for that to be measured.
This test speaks only to the structural conditions the cited data can independently support; it does not constitute a view on future property values, construction costs or government policy, and no such view is expressed or implied.
- Australian Bureau of Statistics (Reference period: June quarter 2026) ‘Number of Dwelling Unit Completions by Sector, Australia: Original (Table 37); Dwelling Units Under Construction by Sector: Original (Table 76)’ [data set], Building Activity, Australia [https://www.abs.gov.au/statistics/industry/building-and-construction/building-activity-australia/latest-release], accessed 31 October 2026.
- CEDA (Committee for Economic Development of Australia) and Urbis Built different: Modern methods of construction (2026) [https://ceda.com.au/research-and-policy/research/infrastructure/built-different-modern-methods-of-construction], accessed 31 October 2026.
ABS material is used under a Creative Commons Attribution 4.0 International licence. Calculations are APN’s and are not attributable to the ABS.
CEDA statements are quoted and attributed; the publication remains the property of the publisher.
Disclaimer
The analysis and information contained in this publication are for general informational and strategic purposes only and do not constitute financial, investment, legal, or any other form of professional advice. Australian Property Network is not a licensed financial advisor. Property values and market conditions can go up or down. Before making any property or investment decisions, you must conduct your own thorough research and seek independent professional advice tailored to your specific circumstances. Images are for illustrative purposes only. E.&O.E.
Findings are presented on the basis of data and evidence alone.