title: "Do Completions Follow Starts? Forty Years of the Gap Between Commencing and Finishing"
url: https://australianproperty.network/apn-investment-conditions-index/supply-pipeline-conditions/do-completions-follow-starts/
date: 2026-11-17
modified: 2026-11-10
lang: en
author: "APN National"
description: "From 1986 to 2019, changes in completions followed changes in commencements two quarters earlier, with a correlation of 0.90. Since 2020 no delay shows a relationship: starts peaked at 229 thousand in 2021 while completions fell."
categories:
  - "Supply Pipeline Conditions"
tags:
  - "24740"
  - "construction"
image: https://australianproperty.network/wp-content/uploads/2026/11/Completions-follow-starts-November-2026.webp
word_count: 1069
---

# Do Completions Follow Starts? Forty Years of the Gap Between Commencing and Finishing

For more than thirty years the number of homes completed followed the number started with a short delay, and since 2020 it has not. From 1986 to 2019 the annual change in completions was correlated at 0.90 with the annual change in commencements two quarters earlier. From 2020 to June 2026 no delay from 0 to 12 quarters gives a correlation above 0.36. Commencements in the year to December 2021 were 229,378, the highest of the period, and completions in the year to December 2022 were 173,903, lower than in the year to March 2020 (198,070).

**Data anchors** · Dwellings commenced in the year to December 2021: **229,378**, the highest of 2020–2026; completed in the year to December 2022: **173,903** · Correlation of annual change in completions with annual change in commencements two quarters earlier: **0.90** in 1986–2019; **0.09** in 2020–2026 (26 quarters) · Supply Pipeline Conditions (24740): **+1.0912σ**, June quarter 2026, position 98.4, ranked against 62 quarters.
Counts are original series summed over four quarters. The ABS does not follow a dwelling from start to finish; these are two separate flows.

#### The question

A home that is started is meant to be finished some time later. If starts rise, completions should follow. How long has that taken, and did it change after 2020? The ABS publishes dwellings commenced and completed each quarter ([ABS, Building Activity, Australia, June quarter 2026](https://www.abs.gov.au/statistics/industry/building-and-construction/building-activity-australia/latest-release)). It does not follow individual dwellings, so the question can only be asked of the two flows together. APN has set out [the gap between approvals and starts](https://australianproperty.network/?p=149528), [months of pipeline](https://australianproperty.network/?p=152844) and [the pipeline against population](https://australianproperty.network/?p=155076); this piece compares starts with finishes.

#### Two flows, forty years

##### Dwellings commenced and completed, Australia, thousands, sum of four quarters, June quarter 1985 to June quarter 2026

- 05010015020025019901995200020052010201520202025CommencementsCompletions204.4180.5
APN calculation based on Australian Bureau of Statistics data: Building Activity (8752.0), dwellings commenced and dwellings completed (sum of the states and territories), original, sum of four quarters, thousands; June quarter 1985 to June quarter 2026.

Commencements peaked at 234.4 thousand in the year to June 2016, and completions peaked at 223.1 thousand in the year to March 2017, three quarters later. Commencements rose again to 229.4 thousand in the year to December 2021. Completions did not: they were 198.1 thousand in the year to March 2020, 173.9 thousand in the year to December 2022, and 180.5 thousand in the year to June 2026, against 204.4 thousand commencements.

| Period | Commencements | Completions |
| ------ | ------------- | ----------- |
| Year to December 2019 | 175,263 | 202,466 |
| Year to December 2020 | 182,998 | 181,340 |
| Year to December 2021 | 229,378 | 178,558 |
| Year to December 2022 | 182,441 | 173,903 |
| Year to December 2023 | 165,856 | 176,637 |
| Year to December 2024 | 169,607 | 179,075 |
| Year to December 2025 | 197,186 | 173,226 |
| Year to June 2026 | 204,440 | 180,501 |

APN calculation based on Australian Bureau of Statistics data: Building Activity (8752.0), dwellings, original, sum of four quarters ending in the stated quarter.

#### Measuring the delay

| Completions measured this many quarters after commencements | 1986–2019: correlation | 2020–2026: correlation |
| ----------------------------------------------------------- | ---------------------------- | ---------------------------- |
| Same quarter | 0.57 | −0.02 |
| 1 | 0.80 | 0.02 |
| 2 | 0.90 | 0.09 |
| 3 | 0.83 | 0.07 |
| 4 | 0.61 | 0.12 |
| 6 | 0.04 | 0.10 |
| 8 | −0.32 | 0.03 |
| 12 | −0.36 | 0.36 |

APN calculation based on Australian Bureau of Statistics data: Building Activity (8752.0). Pearson correlation between the annual change in four-quarter completions and the annual change in four-quarter commencements the stated number of quarters earlier; 123 to 135 quarters in 1986–2019, depending on the delay, and 26 in 2020–2026. The readings overlap, so the quarters are not independent.

In 1986–2019 the annual change in completions followed the annual change in commencements most closely at a delay of two quarters (correlation 0.90), with 0.80 at one quarter, 0.83 at three and 0.61 at four. The correlation was −0.32 at eight quarters. This describes the co-movement of the two flows, not the time a dwelling takes to build: apartments and houses take different times, and a delay of two quarters in the annual figures reflects a mix of builds.

Since 2020 the pattern is not present. Across the 26 quarters from March 2020 the correlation is between −0.02 and 0.36 at every delay from 0 to 12 quarters, the highest being 0.36 at twelve quarters. The sample is short, and the period contains the pandemic closures and a rise in starts in 2021 that completions did not match. It is a period in which commencements and completions did not move together at any delay the data can test.

0.90Correlation at two quarters, 1986–20190.09Correlation at two quarters, 2020–2026204.4kCommencements, year to June 2026, against 180.5k completions

#### What the APN index reads

[Supply Pipeline Conditions (24740)](https://australianproperty.network/apn-codex/series-20000/series-24000/series-24700/series-24740/) is the mean of four components: approvals, commencements, work in progress and a congestion measure. At the June quarter 2026 it stands at +1.0912σ, position 98.4 ranked against 62 quarters. It reads each stage against its own history and does not measure the time between stages, which is what this piece looks at.

#### What this does not show

A correlation between two annual series is not the time an individual dwelling takes to finish, and the quarters in each era overlap, so the readings are not independent. The 2020–2026 sample is 26 quarters. The ABS counts all dwellings alike, including alterations that create dwellings. Cancelled projects, changes in dwelling type and the capacity of the construction industry are not in the series. Nothing here is a forecast of completions from current starts.

**Methodology note.** ABS Building Activity (8752.0): dwellings commenced (from the September quarter 1980) and completed (sum of the states and territories, from the September quarter 1984), original, quarterly. Four-quarter sums are used. For each delay from 0 to 12 quarters, the Pearson correlation is calculated between the annual change in four-quarter completions and the annual change in four-quarter commencements that many quarters earlier, for completions quarters from June 1986 to December 2019 and from March 2020 to June 2026. Supply Pipeline Conditions (24740) is the mean of its four components: +1.0912σ, June quarter 2026, position 98.4 of 62.

**Sources**
Australian Bureau of Statistics (Reference period: June 2026) *Building Activity, Australia* [[https://www.abs.gov.au/statistics/industry/building-and-construction/building-activity-australia/latest-release](https://www.abs.gov.au/statistics/industry/building-and-construction/building-activity-australia/latest-release)], ABS Website, accessed 8 November 2026.
*ABS material is used under a Creative Commons Attribution 4.0 International licence. Calculations, standardisations and index readings are APN’s and are not attributable to the ABS.*

##### Disclaimer

The analysis and information contained in this publication are for general informational and strategic purposes only and do not constitute financial, investment, legal, or any other form of professional advice. Australian Property Network is not a licensed financial advisor. Property values and market conditions can go up or down. Before making any property or investment decisions, you must conduct your own thorough research and seek independent professional advice tailored to your specific circumstances. Images are for illustrative purposes only. E.&O.E.

Findings are presented on the basis of data and evidence alone.
<!-- WP Optimize page cache - https://teamupdraft.com/wp-optimize/ - page NOT cached -->