title: "New South Wales Completed 49,545 Homes in the Year to June 2026. The Accord Needs About 94,900 a Year From Here"
url: https://australianproperty.network/analysis/construction-development-pipeline-analysis/new-housing-supply-forecasts/nsw-pipeline-ledger-completions-accord-june-2026/
date: 2026-11-20
modified: 2026-11-09
lang: en
author: "APN New South Wales"
description: "New South Wales completed 49,545 homes in the year to June 2026, 16.0% more than a year earlier, and 92,270 over the first two years of the Housing Accord: 24.5% of its 377,000 commitment. The rest would need about 94,900 a year."
categories:
  - "New Housing Supply Forecasts"
tags:
  - "21840"
  - "22210"
  - "APN State Desks"
  - "housing supply"
  - "National Housing Accord"
image: https://australianproperty.network/wp-content/uploads/2026/11/NSW-pipeline-ledger-November-2026.webp
word_count: 1354
---

# New South Wales Completed 49,545 Homes in the Year to June 2026. The Accord Needs About 94,900 a Year From Here

#### New South Wales Completed 49,545 Homes in the Year to June 2026. The Accord Needs About 94,900 a Year From Here

APN 22000 Series  ·  [22210 New South Wales Insight](https://australianproperty.network/apn-codex/series-20000/series-22000/series-22200/series-22210/)
Reference I-261120-155247  ·  Observation date: June quarter 2026  ·  Significance Low
Data anchor
[State Completion Lag (21840)](https://australianproperty.network/apn-codex/series-20000/series-21000/series-21800/21840-state-completion-lag/), New South Wales  **−1.1775σ** Q2 2026
The change over the year in the months of work held under construction, against New South Wales’ own history, in standard deviations from its 2011 to 2025 average; position 7.5, ranked against 161 quarters. It lies beyond ±1.0σ: the pipeline shortened faster than usual.

##### Scope and Purpose

Under the National Housing Accord, New South Wales committed to around 377,000 new homes in the five years from 1 July 2024, the commitment the state’s [Department of Planning, Housing and Infrastructure](https://www.planning.nsw.gov.au/policy-and-legislation/housing/housing-targets) has divided into five-year targets for 43 councils. Two of the five years have now passed. The Australian Bureau of Statistics (ABS) counts the homes finished in each state every quarter, and its June quarter 2026 release closes the second Accord year.

This ledger sets the completions against the commitment, and reads the work started and the work still under construction, which together decide how many homes can be finished in the next three years. It follows [APN New South Wales’ analysis of where the state’s population growth comes from](https://australianproperty.network/analysis/demographic-analysis/population-growth-distribution/where-new-south-wales-gets-its-people/).

##### Two Years Completed

New South Wales completed 49,545 dwellings in the year to June 2026, 16.0% more than the 42,725 of the year before, and the most in any four quarters since the year to June 2021. The June quarter alone, 14,060, was the most in a quarter since September 2020. Over the first two Accord years the state completed 92,270 dwellings, the same total the department’s [housing supply dashboard](https://www.planning.nsw.gov.au/data-and-insights/housing-supply) reports, or 24.5% of the commitment with 40% of the time gone.

| Measure | Dwellings |
| ------- | --------- |
| Accord commitment, 1 July 2024 to 30 June 2029 | 377,000 |
| Average pace, a year | 75,400 |
| Completed, year to June 2025 | 42,725 |
| Completed, year to June 2026 | 49,545 |
| Completed in the first two years | 92,270 |
| Share of the commitment completed | 24.5% |
| Remaining | 284,730 |
| Needed a year over the three remaining years | 94,910 |
| Highest year of completions since 1984 (year to June 2019) | 74,683 |
APN calculation based on Australian Bureau of Statistics data: Building Activity, Australia, June quarter 2026, Table 38. The commitment is as published by the NSW Department of Planning, Housing and Infrastructure. Completions are ABS dwelling units completed, original; the department's housing supply dashboard reports the same two-year total.

An even pace would be 75,400 a year. To reach 377,000 by June 2029, the state would need 284,730 more, about 94,910 a year for three years, 1.92 times the past year’s completions. The most New South Wales has completed in any four quarters since the series began in September 1984 is 74,683, in the year to June 2019, 717 below even the average pace.

##### New South Wales: Dwellings Completed and Commenced, Four Quarters to Each Quarter, March 2001 to June 2026

- 20,00030,00040,00050,00060,00070,00080,00020052010201520202025CompletionsCommencementsAccord average pace, 75,400 a year51,80749,545
APN calculation based on Australian Bureau of Statistics data: Building Activity, Australia, June quarter 2026, Tables 34 and 38. Sum of the four quarters to each quarter, original, all dwellings including alterations and additions that create a new dwelling. The dashed line is 377,000 divided by five.

##### What Is Started and What Is Building

Completions follow commencements by a year or more, so the work started sets the ceiling on the work finished. Commencements were 51,807 in the year to June 2026, 10.1% higher than a year earlier and still above completions, so over the year the stock of work under way is not being run down. At the end of June 78,581 dwellings were under construction, below the 80,780 of March and the peak of 89,973 in June 2018.

##### New South Wales: Dwellings Completed in Each Year to June, 2015 to 2026

020,00040,00060,00080,00075,40049,545201520162017201820192020202120222023202420252026
APN calculation based on Australian Bureau of Statistics data: Building Activity, Australia, June quarter 2026, Table 38. Completions over the four quarters to June of each year, original. The gold bar is the year to June 2026. The dashed line is the Accord's average pace.

At the past year’s rate of completion, the work under construction would take 19.0 months to finish, down from 21.3 months a year earlier. [State Completion Lag (21840)](https://australianproperty.network/apn-codex/series-20000/series-21000/series-21800/21840-state-completion-lag/) reads that change: −1.1775σ for New South Wales in the June quarter 2026, the lowest position of the eight states and territories, at 7.5 of 161 quarters, and the largest fall over a year since September 2019. Homes are being finished faster relative to the work in hand.

##### New South Wales: Dwellings Under Construction at Quarter End, March 2001 to June 2026

20,00040,00060,00080,000100,00020052010201520202025Under construction78,581
Source: Australian Bureau of Statistics, Building Activity, Australia, June quarter 2026, Table 77. Dwelling units under construction at the end of each quarter, original.

##### What the Ledger Supports

Completions here are the ABS count of dwelling units completed, original, including those created by alterations and additions. The Accord commitment counts new homes; the department’s dashboard reports the same two-year total from the same source. A completion is counted once, in the quarter the work is finished. The ABS revises recent quarters, so the two-year total may move by a few hundred as the September quarter release is published.

49,545Dwellings completed, year to June 202624.5%Of the 377,000 commitment completed in two years94,910Needed a year from July 2026 to June 202974,683Most completed in any four quarters since 1984

##### What Comes Next

The ABS publishes Building Activity for the September quarter 2026 on 13 January 2027, the first quarter of the third Accord year. It will show whether completions hold near 14,000 a quarter, and whether commencements continue to exceed them.

##### APN Analytical Synthesis

The weight of evidence supports the interpretation that New South Wales is finishing more homes than at any time since 2021, while remaining well short of the pace its Accord commitment requires: the remaining three years would need about 94,910 completions a year, more than the state has completed in any four quarters since 1984. Current conditions are structurally consistent with a pipeline that is shortening, with commencements still above completions.

This output speaks only to the structural conditions the cited data can independently support. It makes no forecast and expresses no view on future policy. The next data point is the ABS Building Activity release for the September quarter 2026.

**Methodology note.** Source: ABS Building Activity, Australia, June quarter 2026: dwelling units commenced (Table 34), completed (Table 38) and under construction at quarter end (Table 77), New South Wales, total sectors, original, September quarter 1984 to June quarter 2026. Four-quarter sums add the quarter shown and the three before it; the Accord years end in June. The average pace is 377,000 divided by five, and the remaining annual need is the remainder divided by three. Months of work under construction is dwellings under construction at the end of June divided by a twelfth of completions over the year. State Completion Lag (21840) reads the change over the year in those months, against New South Wales’ 2011 to 2025 average. Values are as published and are subject to revision.

**Sources**
Australian Bureau of Statistics (Reference period: June quarter 2026) *Building Activity, Australia* [[https://www.abs.gov.au/statistics/industry/building-and-construction/building-activity-australia/jun-2026](https://www.abs.gov.au/statistics/industry/building-and-construction/building-activity-australia/jun-2026)], ABS Website, accessed 9 November 2026.- NSW Department of Planning, Housing and Infrastructure (Reference period: updated 12 October 2026) *Housing supply dashboard* [[https://www.planning.nsw.gov.au/data-and-insights/housing-supply](https://www.planning.nsw.gov.au/data-and-insights/housing-supply)], accessed 26 October 2026.- NSW Department of Planning, Housing and Infrastructure *Housing targets* [[https://www.planning.nsw.gov.au/policy-and-legislation/housing/housing-targets](https://www.planning.nsw.gov.au/policy-and-legislation/housing/housing-targets)], accessed 26 October 2026.
*ABS material is used under a Creative Commons Attribution 4.0 International licence. Calculations, standardisations and index readings are APN’s and are not attributable to the ABS.*

*NSW Government figures are quoted from the department’s published pages.*

##### Disclaimer

The analysis and information contained in this publication are for general informational and strategic purposes only and do not constitute financial, investment, legal, or any other form of professional advice. Australian Property Network is not a licensed financial advisor. Property values and market conditions can go up or down. Before making any property or investment decisions, you must conduct your own thorough research and seek independent professional advice tailored to your specific circumstances. Images are for illustrative purposes only. E.&O.E.