title: "Canberra Is Starting More Homes. Is It Finishing Enough of Them?"
url: https://australianproperty.network/analysis/construction-development-pipeline-analysis/canberra-starting-more-homes-finishing-enough/
date: 2026-11-03
modified: 2026-10-27
lang: en
author: "APN Australian Capital Territory"
description: "Canberra completed 3,800 homes in 2025-26, the fewest since 2015-16, while starts more than doubled. Reaching the territory's Accord share of 21,000 by June 2029 would take 4,361 completions a year."
categories:
  - "Construction & Development Pipeline Analysis"
tags:
  - "21840"
  - "22270"
  - "APN State Desks"
  - "Australian Capital Territory (ACT)"
image: https://australianproperty.network/wp-content/uploads/2026/10/Canberra-starting-more-homes-October-2026.webp
word_count: 2209
---

# Canberra Is Starting More Homes. Is It Finishing Enough of Them?

#### Canberra Is Starting More Homes. Is It Finishing Enough of Them?

APN 22000 Series  ·  [22270 Australian Capital Territory Insight](https://australianproperty.network/apn-codex/series-20000/series-22000/series-22200/series-22270/)
Reference I-271026-154298  ·  Observation date: June quarter 2026  ·  Significance Low
Data anchor
[State Completion Lag (21840)](https://australianproperty.network/apn-codex/series-20000/series-21000/series-21800/21840-state-completion-lag/), Australian Capital Territory  **+0.8511σ** Q2 2026
The reading compares the territory with its own history, in standard deviations from its 2011 to 2025 average. No node lies beyond ±1.0σ, on which the significance rating rests.

##### Scope and Purpose

The Australian Capital Territory completed 3,800 homes in 2025–26, the fewest in any financial year since 2015–16. It started 4,935, more than twice the 2,085 of the year before, which was the fewest since 2005–06. This output sets the territory’s housing pipeline against the two targets it is measured by: its share of the national Housing Accord, and the ACT Government’s commitment to enable 30,000 homes by the end of 2030. It asks what the pace of completions so far implies, what the rise in starts can and cannot carry, and what the figures cannot yet show.

The building figures come from the Australian Bureau of Statistics (ABS) [*Building Activity, Australia*](https://www.abs.gov.au/statistics/industry/building-and-construction/building-activity-australia/jun-2026), June quarter 2026, and [*Building Approvals, Australia*](https://www.abs.gov.au/statistics/industry/building-and-construction/building-approvals-australia/aug-2026), August 2026. The targets come from the ACT Government’s [Housing Supply and Land Release Program 2026–27 to 2030–31](https://www.planning.act.gov.au/__data/assets/pdf_file/0005/3080165/2026-HSLRP_WEB.pdf) and [2026–27 Budget Housing Statement](https://www.treasury.act.gov.au/__data/assets/pdf_file/0008/3080978/2026-27-ACT-Budget-Housing-Statement.pdf), and the national outlook from the National Housing Supply and Affordability Council’s [*State of the Housing System 2026*](https://nhsac.gov.au/sites/nhsac.gov.au/files/2026-04/ar-state-housing-system-2026.pdf). APN reads the time the territory’s pipeline would take to clear in [State Completion Lag (21840)](https://australianproperty.network/apn-codex/series-20000/series-21000/series-21800/21840-state-completion-lag/).

##### Two Targets That Count Different Things

The Housing Accord aims for 1.2 million new homes nationally over the five years from mid-2024. The territory’s land release program puts its share at “around 21,000 homes by 2028–29”; the Council apportions the same 21,000 by population, and notes that the shares are not formally agreed between governments. The Council counts gross new homes completed, as the ABS records them, so the share can be read against ABS completions. Spread evenly, it is about 4,200 completions a year.

The 30,000 is a different measure. The Housing Statement describes it as a commitment to *enable* 30,000 more homes, including 5,000 public, community and affordable rental dwellings, by the end of 2030, through land release, planning reform and direct funding. Homes enabled are not homes completed, and the documents do not state the count’s starting date or how it is tallied. **This output therefore tests completions against the Accord share, and does not set them against the 30,000.**

##### Completions Against the Accord Share

In the first two years of the Accord period the territory completed 4,116 and 3,800 homes, 7,916 in all, 94% of an even pace. Reaching 21,000 by June 2029 would take 4,361 completions a year for the next three years. The territory last completed more than that in 2022–23, when it completed 5,424, the most of any financial year since the series began in 1984–85.

##### Australian Capital Territory: Dwelling Units Completed Against the Pace of the Territory’s Accord Share, 2018–19 to 2025–26

- 01,0002,0003,0004,0005,0006,000Completed4,200 a year: 21,000 over five years from July 20243,80020192020202120222023202420252026
APN calculation based on Australian Bureau of Statistics data: Building Activity, Australia, June quarter 2026, Australian Capital Territory. Financial-year sums, original, labelled by the year in which each ends; the gold bar is 2025–26. The Accord period began on 1 July 2024. The reference line divides the territory’s share of around 21,000 homes evenly over five years.

The Council’s early-2026 outlook, made before the disruption to fuel and materials prices that followed, estimated that the territory would complete about 22,000 homes over the Accord period and reach its share by the June quarter 2029. On that estimate the ACT is one of three jurisdictions expected to reach its share within or just after the period, and the Budget papers describe it as one of only three on track. An outcome of 22,000 would need about 4,695 completions a year from here. The territory exceeded that in 7 financial years since 1984–85, all between 2012–13 and 2022–23, and in none of the three since. The estimate is a forecast rather than a count. The June quarter 2026, the first full quarter recorded after it, brought 617 completions, the fewest in any quarter since the March quarter 2025.

##### The Rise in Starts Rests on a Few Quarters

Starts rose +136.7% in 2025–26 while completions fell 7.7%. Of the 4,935 starts, 2,030, or 41%, came in the September quarter 2025 alone. In a territory of the ACT’s size a single apartment project moves the quarterly count, so a year’s starts can depend on a handful of buildings.

##### Australian Capital Territory: Dwelling Units Commenced and Completed, 1984–85 to 2025–26, Number a Year

01,0002,0003,0004,0005,0006,0007,000198519901995200020052010201520202025CompletedCommenced4,9353,800
APN calculation based on Australian Bureau of Statistics data: Building Activity, Australia, June quarter 2026, Australian Capital Territory. Sums of the four quarters of each financial year (September to June), original. Years are labelled by the year in which they end.

Approvals show the same pattern. The territory approved 2,840 dwellings in 2024–25, the fewest in any financial year since 2007–08, and 4,128 in 2025–26. The rolling twelve-month total reached 4,812 in the twelve months to February 2026 and has since eased to 3,751 in the twelve months to August 2026. Approvals usually precede starts by some months, so the easing is the next thing to read in the starts figures.

##### Australian Capital Territory: Dwelling Units Approved, Twelve Months to June 2015 to Twelve Months to August 2026

01,0002,0003,0004,0005,0006,0007,0008,000201620182020202220242026Approved, twelve months to date3,751
APN calculation based on Australian Bureau of Statistics data: Building Approvals, Australia, August 2026, Table 9 (A422863J). Rolling twelve-month sums of monthly dwelling units approved, original. Approvals include alterations that create dwellings.

##### A Longer Wait for the Homes Under Construction

At the end of June 2026 the territory had 6,262 homes under construction, against 5,129 a year earlier, though below the 8,286 of December 2018. At the rate homes were completed over the last four quarters, that stock would take 19.8 months to finish, up from 15.0 a year earlier and against an average of 15.9 months from 2011 to 2025. It is the 11th longest of the 165 quarters since June 1985.

##### Australian Capital Territory: Months of Pipeline, March Quarter 2011 to June Quarter 2026

05101520253020122014201620182020202220242026Months of pipeline2011 to 2025 average19.8
APN calculation based on Australian Bureau of Statistics data: Building Activity, Australia, June quarter 2026, Australian Capital Territory. Dwelling units under construction at quarter end divided by the average monthly completions of the latest four quarters, original.

[State Completion Lag (21840)](https://australianproperty.network/apn-codex/series-20000/series-21000/series-21800/21840-state-completion-lag/) reads the change in months of pipeline over the year: +0.8511σ for the June quarter 2026 against the territory’s 2011 to 2025 average, with a position of 86.9 ranked against 161 quarters. The pipeline has lengthened because starts rose while completions fell. A longer pipeline can mean projects taking longer to build, or a shift towards apartment buildings, which are completed all at once; the totals do not distinguish the two.

| Financial year | Approved | Commenced | Completed | Under construction at 30 June | Months of pipeline at 30 June |
| -------------- | -------- | --------- | --------- | ----------------------------- | ----------------------------- |
| 2018–19 | 6,180 | 6,158 | 4,818 | 7,403 | 18.4 |
| 2019–20 | 4,928 | 5,092 | 4,938 | 7,504 | 18.2 |
| 2020–21 | 5,017 | 5,168 | 5,130 | 7,437 | 17.4 |
| 2021–22 | 6,195 | 5,612 | 4,737 | 8,273 | 21.0 |
| 2022–23 | 3,857 | 3,944 | 5,424 | 6,741 | 14.9 |
| 2023–24 | 4,549 | 4,504 | 4,078 | 7,163 | 21.1 |
| 2024–25 | 2,840 | 2,085 | 4,116 | 5,129 | 15.0 |
| 2025–26 | 4,128 | 4,935 | 3,800 | 6,262 | 19.8 |
APN calculation based on Australian Bureau of Statistics data: Building Activity, Australia, June quarter 2026, Australian Capital Territory. APN calculation based on Australian Bureau of Statistics data: Building Approvals, Australia, August 2026, Table 9 (A422863J). Financial-year sums of quarterly or monthly figures, original. Months of pipeline as defined under the chart above.

##### Land Release and Private Building

The ACT Government is the only seller of new residential land in the territory, through the Suburban Land Agency, and private building on established land adds to it. The [ACT Audit Office](https://www.audit.act.gov.au/__data/assets/pdf_file/0007/2997547/Report-7-2025-2024-25-Financial-Audit-Program-Overall-Results.pdf) reports that the Suburban Land Agency released fewer residential dwellings than planned in each of the four years to 2024–25: 4,939 were identified for release in 2024–25, and the number released was 24% below target. The land release program sets out land for 25,794 homes over the five years from 2026–27, and estimates that the private sector has added around 1,000 to 1,500 homes a year, mostly apartments and townhouses in established suburbs. Released land becomes completed homes only after sale, approval and construction, so these releases bear on completions late in the Accord period and after it.

##### What the Figures Cannot Separate

**Houses and apartments.** The ABS state tables give totals for starts, completions and homes under construction. They do not show whether the longer pipeline reflects slower building or a larger share of apartments.- **The Missing Middle reform.** Since 1 July 2026 low-rise “missing middle” housing has been permitted in the RZ1 zone, up to two storeys, with further opportunities in RZ2, up to three. Its uptake would show in approvals of semi-detached, row, terrace and townhouse dwellings; the totals cited here combine them with apartments, and two months of post-reform data are too few to read.- **Homes enabled.** Land release, planning approvals and funding commitments count towards the 30,000; none is a completion, and no public series counts them on one basis.- **Net additions.** Completions are gross: homes demolished to make way for new ones are not subtracted.- **Revisions.** Quarterly building figures are revised, and the latest quarters most.

3,800Homes completed, 2025–264,935Homes started, 2025–264,361Completions a year needed to reach 21,000 by June 202919.8Months of pipeline, June quarter 2026

##### What the Next Figures Will Read

- **Completions in the September quarter 2026.** The ABS *Building Activity* for that quarter, due on 13 January 2027, gives the first quarter of the Accord’s third year, against the 4,361 a year now needed.- **Approvals by type.** Monthly approvals of semi-detached, row, terrace and townhouse dwellings through December 2026 give the first two quarters of the Missing Middle reform.- **The Council’s next estimate.** The National Housing Supply and Affordability Council’s quarterly reports update the expected date by which each jurisdiction reaches its share.

##### APN Analytical Synthesis

The weight of evidence supports the interpretation that the territory’s completions are running behind the pace of its Accord share, and that the rise in starts does not yet change that. Completions have stayed below 4,200 in each of the last three years, the next three would need 4,361 a year, and the homes under construction would take longer to finish than in all but 10 of 165 quarters since June 1985. [State Completion Lag (21840)](https://australianproperty.network/apn-codex/series-20000/series-21000/series-21800/21840-state-completion-lag/) at +0.8511σ records the lengthening. The forecast that places the territory on track predates the latest year of completions.

Current conditions are structurally consistent with a pipeline in which more homes are waiting to be finished than a year ago and fewer are being finished each quarter. This output speaks only to the structural conditions the cited data can independently support. It makes no forecast and expresses no view on future prices or policy. The next data point is the ABS *Building Activity* for the September quarter 2026, due on 13 January 2027.

**Methodology note.** Sources: ABS Building Activity, Australia, June quarter 2026 (Australian Capital Territory, dwelling units commenced, completed and under construction, original); ABS Building Approvals, Australia, August 2026 (Table 9, Australian Capital Territory, total dwelling units approved, original, A422863J); ACT Government, Housing Supply and Land Release Program 2026–27 to 2030–31 and 2026–27 Budget Housing Statement; ACT Audit Office, Report No. 7/2025, paragraphs 5.30 to 5.32; National Housing Supply and Affordability Council, State of the Housing System 2026, section 4.3.1 and Table 4.1, all read 27 October 2026. A financial year is the four quarters from September to June. Months of pipeline is the number of dwellings under construction at quarter end divided by one-twelfth of completions over the latest four quarters. The completions needed is the Accord share of 21,000 less completions in 2024–25 and 2025–26, divided by the three remaining years. State Completion Lag (21840) reads the change in months of pipeline over the year against the territory’s own 2011 to 2025 average; its position ranks the latest quarter against every earlier quarter with full data. Values are as published at each release and are subject to revision.

**Sources**
- ACT Audit Office *2024-25 Financial Audit Program: Overall Results, Report No. 7/2025* [[https://www.audit.act.gov.au/__data/assets/pdf_file/0007/2997547/Report-7-2025-2024-25-Financial-Audit-Program-Overall-Results.pdf](https://www.audit.act.gov.au/__data/assets/pdf_file/0007/2997547/Report-7-2025-2024-25-Financial-Audit-Program-Overall-Results.pdf)], accessed 27 October 2026.- ACT Government *2026-27 Budget Housing Statement* [[https://www.treasury.act.gov.au/__data/assets/pdf_file/0008/3080978/2026-27-ACT-Budget-Housing-Statement.pdf](https://www.treasury.act.gov.au/__data/assets/pdf_file/0008/3080978/2026-27-ACT-Budget-Housing-Statement.pdf)], accessed 27 October 2026.- ACT Government *Housing Supply and Land Release Program 2026-27 to 2030-31* [[https://www.planning.act.gov.au/__data/assets/pdf_file/0005/3080165/2026-HSLRP_WEB.pdf](https://www.planning.act.gov.au/__data/assets/pdf_file/0005/3080165/2026-HSLRP_WEB.pdf)], accessed 27 October 2026.- Australian Bureau of Statistics (Reference period: August 2026) *Building Approvals, Australia* [[https://www.abs.gov.au/statistics/industry/building-and-construction/building-approvals-australia/aug-2026](https://www.abs.gov.au/statistics/industry/building-and-construction/building-approvals-australia/aug-2026)], ABS Website, accessed 27 October 2026.- Australian Bureau of Statistics (Reference period: June 2026) *Building Activity, Australia* [[https://www.abs.gov.au/statistics/industry/building-and-construction/building-activity-australia/jun-2026](https://www.abs.gov.au/statistics/industry/building-and-construction/building-activity-australia/jun-2026)], ABS Website, accessed 27 October 2026.- National Housing Supply and Affordability Council *State of the Housing System 2026* [[https://nhsac.gov.au/sites/nhsac.gov.au/files/2026-04/ar-state-housing-system-2026.pdf](https://nhsac.gov.au/sites/nhsac.gov.au/files/2026-04/ar-state-housing-system-2026.pdf)], accessed 27 October 2026.
*ABS material is used under a Creative Commons Attribution 4.0 International licence. Calculations, standardisations and index readings are APN’s and are not attributable to the ABS.*

*Figures from the ACT Government, the ACT Audit Office and the National Housing Supply and Affordability Council are quoted from the publishers’ published material and remain the property of the publishers.*

##### Disclaimer

The analysis and information contained in this publication are for general informational and strategic purposes only and do not constitute financial, investment, legal, or any other form of professional advice. Australian Property Network is not a licensed financial advisor. Property values and market conditions can go up or down. Before making any property or investment decisions, you must conduct your own thorough research and seek independent professional advice tailored to your specific circumstances. Images are for illustrative purposes only. E.&O.E.

Findings are presented on the basis of data and evidence alone.